{"id":20086190,"date":"2022-04-08T12:30:00","date_gmt":"2022-04-08T07:00:00","guid":{"rendered":"https:\/\/www.thethirdpole.net\/?p=86190"},"modified":"2022-04-21T10:10:01","modified_gmt":"2022-04-21T04:40:01","slug":"questions-over-rooppur-nuclear-power-plant-bangladesh","status":"publish","type":"post","link":"https:\/\/dialogue.earth\/en\/energy\/questions-over-rooppur-nuclear-power-plant-bangladesh\/","title":{"rendered":"Questions over Russia-funded nuclear power plant in Bangladesh"},"content":{"rendered":"\n<p class=\"has-drop-cap\">Russia\u2019s invasion of Ukraine could delay the completion of Bangladesh\u2019s first nuclear power plant. With a planned capacity of <a href=\"https:\/\/world-nuclear.org\/information-library\/country-profiles\/countries-a-f\/bangladesh.aspx\">2,400 megawatts<\/a> \u2013 around twice the generating capacity of the <a href=\"https:\/\/dialogue.earth\/en\/energy\/chinese-backed-electricity-plant-endangers-hilsa-sanctuary\/\">Payra coal power project<\/a> \u2013 any delays to the Rooppur nuclear plant, scheduled to be <a href=\"https:\/\/www.power-technology.com\/projects\/rooppur-nuclear-power-plant-ishwardi\/\">completed by 2024<\/a>, would leave a significant gap in Bangladesh\u2019s power sector development. The Third Pole has learned that officials are already preparing backup plans.<\/p>\n\n\n\n<p>Russia is providing 90% of the funding for the USD 12.65 billion project, and construction is being carried out by a Russian state-owned company in the west-central district of Pabna. The government of Bangladesh is funding the remaining 10%. Rooppur is part of Bangladesh\u2019s plan to shift its reliance from highly polluting coal and other fossil fuels.<\/p>\n\n\n\n<p>Shortly after the invasion of Ukraine on 24 February, the US, EU and UK <a href=\"https:\/\/www.economist.com\/briefing\/2022\/03\/05\/western-sanctions-on-russia-are-like-none-the-world-has-seen\">implemented sanctions<\/a> on Russian banks and their access to SWIFT, an international payment system. As <a href=\"https:\/\/www.ft.com\/content\/477c31ba-7c8c-45cf-8535-8e90b49aaad4\">more rounds<\/a> of sanctions are imposed, the environment is tightening for Russian businesses and the organisations they transact with. The Ministry of Power, Energy and Mineral Resources is sufficiently alarmed at the potential loss of resources for the nuclear power plant that it has started to prepare for alternatives such as coal and renewable energy sources.<\/p>\n\n\n\n<p>Nasrul Hamid, the state minister for the Ministry of Power, Energy and Mineral Resources, said Bangladesh\u2019s current power generation capacity is 25,500 MW. \u201cOur estimate is by 2030 we will require a staggering 40,000 MW of electricity including the 2,400 MW from Rooppur power plant,\u201d said Hamid.<\/p>\n\n\n\n<p>He added: \u201cWe are working to ensure that we get the 40,000 MW [by] 2030 assuming that we may not get the 2,400 MW from the Rooppur nuclear power plant.<\/p>\n\n\n\n<div class=\"wp-block-cd-pull-quote block--pull-quote\"><div class=\"block--pull-quote__wrapper\"><blockquote class=\"block--pull-quote__quote\">If construction of the Rooppur nuclear power plant is hampered, possibly we will not see any problem in getting power from other backup coal projects<\/blockquote><cite class=\"block--pull-quote__cite\">Nasrul Hamid, state minister for the Ministry of Power, Energy and Mineral Resources<\/cite><\/div><\/div>\n\n\n\n<p>\u201cIf construction of the Rooppur nuclear power plant is hampered, possibly we will not see any problem in getting power from other backup coal projects and some renewable sources.\u201d<\/p>\n\n\n\n<p>Ijaz Hossain, an <a href=\"https:\/\/www.buet.ac.bd\/info\/Department\/EngineeringFaculty\">energy expert and dean<\/a> of the faculty of engineering at Bangladesh University of Engineering and Technology (BUET), told The Third Pole that the economic sanctions imposed on Russia would impact the completion of the Rooppur project.<\/p>\n\n\n\n<p>\u201cRussia is a military power, not an economic power,\u201d Hossain said. \u201cIf the war between Russia and Ukraine lingers, it would further weaken Russia economically. In that case, Russia would not be able to continue the construction of the Rooppur power project; it will be delayed.\u201d<\/p>\n\n\n\n<h2 class=\"wp-block-heading\" id=\"h-assurances-that-rooppur-is-on-track\">Assurances that Rooppur is on track<\/h2>\n\n\n\n<p>In the first week of March, the Russian government assured Bangladesh\u2019s Ministry of Science and Technology, which oversees the construction of the 2,400 MW plant, that the project will be completed on time despite the sanctions, Ziaul Hasan, <a href=\"http:\/\/npmis.mopa.gov.bd\/mopateldir\/contact\/indexPublic?organization=1062\">secretary<\/a> of the Ministry of Science and Technology, told The Third Pole.<\/p>\n\n\n\n<p>\u201cThe Russian government has given us a letter that the \u2018special military operation\u2019 in Ukraine will not hamper the construction of the Rooppur nuclear power plant. They will finish the project in time. We want to believe it,\u201d said Hasan.<\/p>\n\n\n\n<p>\u201cRussia is a big international power, and I think they would find an alternative mode of funds transfer to fund the project,\u201d he pointed out. <\/p>\n\n\n\n<p>Rosatom, Russia\u2019s state-owned atomic power corporation, will supply uranium and other materials needed for running the Rooppur plant, Hasan said. At the time of writing, the company, which is the world\u2019s biggest supplier of nuclear fuel and reactors, had not been sanctioned due to <a href=\"https:\/\/www.reuters.com\/world\/europe\/us-weighs-sanctions-russian-nuclear-power-supplier-rosatom-bloomberg-2022-03-09\/\">concerns at the impact<\/a> on the operations of nuclear power plants worldwide.<\/p>\n\n\n\n<div class=\"wp-block-cd-story-image block--story-image\" itemscope itemtype=\"http:\/\/schema.org\/ImageObject\"><div class=\"block--story-image__column\"><div class=\"block--story-image__image\"><img class=\"lazy\" data-src=\"https:\/\/dialogue.earth\/content\/uploads\/2022\/04\/20220507_Rooppur-nuclear-power-plant-satellite_Maxar-Technologies-scaled.jpg\" data-srcset=\"https:\/\/dialogue.earth\/content\/uploads\/2022\/04\/20220507_Rooppur-nuclear-power-plant-satellite_Maxar-Technologies-768x432.jpg 768w, https:\/\/dialogue.earth\/content\/uploads\/2022\/04\/20220507_Rooppur-nuclear-power-plant-satellite_Maxar-Technologies-1024x576.jpg 1024w, https:\/\/dialogue.earth\/content\/uploads\/2022\/04\/20220507_Rooppur-nuclear-power-plant-satellite_Maxar-Technologies-1400x788.jpg 1400w, https:\/\/dialogue.earth\/content\/uploads\/2022\/04\/20220507_Rooppur-nuclear-power-plant-satellite_Maxar-Technologies-1800x1013.jpg 2000w, https:\/\/dialogue.earth\/content\/uploads\/2022\/04\/20220507_Rooppur-nuclear-power-plant-satellite_Maxar-Technologies-scaled.jpg\" data-sizes=\"(max-width: 600px) 768px, (max-width: 999px) 1024px, (max-width: 1400px) 1400px, (max-width: 2000px) 2000px, 2560px\" alt=\"satellite photo of Rooppur nuclear power plant in Bangladesh\"\/><\/div><div class=\"block--story-image__content\"><div itemprop=\"caption\" class=\"block--story-image__caption\">The Rooppur nuclear power plant is being built in the west-central district of Pabna beside the transboundary Ganga River, known as the Padma in Bangladesh (Image \u00a9 Maxar Technologies via Google Earth Pro)<\/div><\/div><\/div><meta itemprop=\"contentUrl\" content=\"https:\/\/dialogue.earth\/content\/uploads\/2022\/04\/20220507_Rooppur-nuclear-power-plant-satellite_Maxar-Technologies-scaled.jpg\"\/><meta itemprop=\"contentSize\" content=\"668 KB\"\/><meta itemprop=\"height\" content=\"1440\"\/><meta itemprop=\"width\" content=\"2560\"\/><meta itemprop=\"author\"\/><meta itemprop=\"representativeOfPage\" content=\"true\"\/><\/div>\n\n\n\n<p>Hasan said that construction has not been interrupted and that 80% of the work on the project is finished. According to statements&nbsp;from Rosatom and equipment exporter&nbsp;JSC Atomstroyexport (a subsidiary of Rosatom), as of 6 April shipments of equipment from Russia had <a href=\"https:\/\/www.tbsnews.net\/bangladesh\/russia-keeps-equipment-shipment-rooppur-plant-uninterrupted-397662\">not been interrupted<\/a> and progress at the plant <a href=\"https:\/\/thefinancialexpress.com.bd\/national\/generator-stator-installed-at-rooppur-nuclear-power-plant-1649240629\">was continuing<\/a>.<\/p>\n\n\n\n<p>But \u201cif the war in Ukraine prolongs, we fear that there could be some problems in implementing the Rooppur nuclear project\u201d, said the secretary.<\/p>\n\n\n\n<p>There are other factors that could jeopardise the project, pointed out Hossain, the dean at BUET. \u201cWestern countries may pressure Bangladesh to stop economic engagement with Moscow in case the hostilities between Russia and the US-led western countries continue to escalate,\u201d he said.<\/p>\n\n\n\n<h2 class=\"wp-block-heading\" id=\"h-rooppur-development-and-the-energy-transition\">Rooppur, development and the energy transition<\/h2>\n\n\n\n<p>Bangladesh has factored the 2,400 MW from the Rooppur nuclear plant into its <a href=\"https:\/\/www.tbsnews.net\/bangladesh\/energy\/govt-plans-generating-more-2883-mw-power-next-6-yrs-357031\">six-year plan<\/a> for electricity generation. In 2026, it plans to add 502 MW of generation capacity to the grid: an important milestone year for the country in terms of its socioeconomic development, as it is expected to <a href=\"https:\/\/www.un.org\/development\/desa\/dpad\/2021\/graduation-of-bangladesh-lao-peoples-democratic-republic-and-nepal-from-the-ldc-category\/#:~:text=the%2520LDC%2520category-,Graduation%2520of%2520Bangladesh%252C%2520Lao%2520People's%2520Democratic%2520Republic,Nepal%2520from%2520the%2520LDC%2520category&amp;text=On%252024%2520November%25202021%252C%2520the,the%2520least%2520developed%2520country%2520category.\">graduate<\/a> from the Least Developed Countries (LDC) status to a developing country.<\/p>\n\n\n\n<p>One of the <a href=\"https:\/\/reliefweb.int\/report\/bangladesh\/bangladesh-climate-and-disaster-risk-atlas-exposures-vulnerabilities-and-risks#:~:text=Bangladesh%2C%20considered%20to%20be%20the,its%20topography%20and%20geographical%20location.\">most-climate vulnerable<\/a> countries in the world, Bangladesh has pledged to cut its <a href=\"https:\/\/dialogue.earth\/en\/hub\/energy-transition-2\/\">emissions<\/a> of heat-trapping gases by 22% by 2030 compared with 2012. The government plans for nuclear power to account for about 10% of <a href=\"https:\/\/rooppurnpp.portal.gov.bd\/sites\/default\/files\/files\/rooppurnpp.portal.gov.bd\/notices\/7e349f02_ec26_4a27_be29_66ef81041cb8\/A%20snapshot%20on%20Rooppur%20Nuclear%20Power%20Plant%20Project.pdf\">total power generation<\/a> after 2030.<\/p>\n\n\n\n<h2 class=\"wp-block-heading\" id=\"h-nuclear-plant-has-been-60-years-in-the-making\">Nuclear plant has been 60 years in the making<\/h2>\n\n\n\n<p>Rooppur was planned in the <a href=\"https:\/\/www.nuclearasia.com\/feature\/history-nuclear-power-bangladesh-road-rooppur-n-plant-project\/1531\/\">early 1960s<\/a> when Bangladesh was part of Pakistan \u2013 one of the <a href=\"https:\/\/www.jstor.org\/stable\/2706560\">two nuclear states<\/a> in South Asia. A study <a href=\"https:\/\/www.scirp.org\/pdf\/EPE_2013112114243660.pdf\">found<\/a> the project to be feasible. But the government at the time shelved it for unknown reasons.<\/p>\n\n\n\n<p>After gaining independence in 1971, the government explored the possibility of reviving the project, but hit snags. In the 1980s, governments made further unsuccessful attempts to implement it.<\/p>\n\n\n\n<p>The Rooppur nuclear power plant resurfaced in 2007-08, when the country had a <a href=\"https:\/\/www.reuters.com\/article\/idUSDHA58449\">huge power deficit<\/a> resulting in outages across the country. The military-led government discussed it with China and South Korea but discarded the plan.<\/p>\n\n\n\n<a class=\"wp-block-cd-related-news alignright block--related-news loading\" data-post-id=\"20025150\"><div class=\"block--related-news__image\"><\/div><div class=\"block--related-news__content\"><span class=\"block--related-news__heading\">Recommended<\/span><span class=\"block--related-news__title\"><\/span><\/div><\/a>\n\n\n\n<p>Then, on 29 December 2008, the present government led by Sheikh Hasina came to power. It <a href=\"https:\/\/www.rusatom-overseas.com\/media\/mass-media-about-us\/rooppur-nuclear-power-plant-symbol-of-bangladesh-russian-friendship.html\">revived the construction<\/a> of the Rooppur nuclear power plant, this time with Russian support. In 2011, the two countries reached an agreement to cooperate on the construction of the plant. The <a href=\"http:\/\/www.baec.gov.bd\/\">Bangladesh Atomic Energy Commission<\/a> and <a href=\"https:\/\/www.rosatom.ru\/en\/index.html\">Rosatom<\/a> are the lead agencies for the Rooppur nuclear power project.<\/p>\n\n\n\n<p>In 2016, the two governments <a href=\"https:\/\/www.neimagazine.com\/news\/newsrussia-initials-credit-agreement-with-bangladesh-for-rooppur-npp-4907672\/\">signed<\/a> an agreement for the financing of the project, with Russian state banks providing USD 12.65 billion. Construction started in 2017, carried out by Rosatom under an EPC (engineering, procurement and construction) contract. Under the contract, JSC Atomstroyexport, a Russian engineering company and fully owned Rosatom subsidiary, provides all equipment, machinery, scientists, engineers, technical personnel and other staff for the project.<\/p>\n\n\n\n<p>Hasan, the secretary of the Ministry of Science and Technology, said that the rate of interest is 1.75% plus service charges, and the total rate of interest would not exceed 2%.<\/p>\n\n\n\n<div class=\"wp-block-cd-pull-quote block--pull-quote\"><div class=\"block--pull-quote__wrapper\"><blockquote class=\"block--pull-quote__quote\">If the war in Ukraine prolongs, we fear that there could be some problems in implementing the Rooppur nuclear project<\/blockquote><cite class=\"block--pull-quote__cite\">Ziaul Hasan, secretary of the Ministry of Science and Technology<\/cite><\/div><\/div>\n\n\n\n<p>He said the Bangladeshi government has a 10-year grace period. In 2027, it will start to pay the debt back over the following 20 years.<\/p>\n\n\n\n<p>The Russian state-owned company is training local technicians in Bangladesh, who will take over the operation of the plant 10 years after its launch.<\/p>\n\n\n\n<h2 class=\"wp-block-heading\" id=\"h-plans-for-bangladesh-s-second-nuclear-power-plant\">Plans for Bangladesh\u2019s second nuclear power plant<\/h2>\n\n\n\n<p>In October last year, prime minister Hasina <a href=\"https:\/\/thefinancialexpress.com.bd\/national\/govt-looks-for-suitable-place-to-set-up-second-nuclear-plant-pm-says-1633869922\">announced<\/a> a plan for a second nuclear power plant in Bangladesh. The Atomic Energy Commission has already suggested some sites for the second nuclear power plant, Hasan said. A government source, speaking on condition of anonymity, told The Third Pole that the government has yet to decide about the second project, and that the Russian government was interested in implementing it.<\/p>\n\n\n\n<p>Hossain, the professor at BUET, cautioned: \u201cGiven the international order after the invasion of Ukraine, I think the government would not be in a position to build the second nuclear plant with Russian support.\u201d<\/p>\n","protected":false},"excerpt":{"rendered":"<p>Officials are preparing to make up for an electricity shortfall if sanctions delay completion of the Rooppur nuclear power plant<\/p>\n","protected":false},"author":20000283,"featured_media":20086240,"comment_status":"open","ping_status":"closed","sticky":false,"template":"","format":"standard","meta":{"_acf_changed":false,"footnotes":""},"categories":[757],"tags":[17073,544,547,570],"hashtags":[],"country":[20000116],"class_list":["post-20086190","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-energy","tag-energy-transition","tag-finance","tag-fossil-fuels","tag-nuclear","country-bangladesh"],"acf":[],"yoast_head":"<!-- This site is optimized with the Yoast SEO Premium plugin v26.0 (Yoast SEO v26.0) - https:\/\/yoast.com\/wordpress\/plugins\/seo\/ -->\n<title>Questions over Rooppur nuclear plant in Bangladesh | Dialogue Earth<\/title>\n<meta name=\"description\" content=\"Officials are preparing to make up for an electricity shortfall if sanctions delay completion of Bangladesh&#039;s first nuclear power plant\" \/>\n<meta name=\"robots\" content=\"index, follow, max-snippet:-1, max-image-preview:large, max-video-preview:-1\" \/>\n<link rel=\"canonical\" href=\"https:\/\/dialogue.earth\/en\/energy\/questions-over-rooppur-nuclear-power-plant-bangladesh\/\" \/>\n<meta property=\"og:locale\" content=\"en_US\" \/>\n<meta property=\"og:type\" content=\"article\" \/>\n<meta property=\"og:title\" content=\"Questions over Russia-funded nuclear power plant in Bangladesh\" \/>\n<meta property=\"og:description\" content=\"Officials are preparing to make up for an electricity shortfall if sanctions delay completion of the Rooppur nuclear power plant\" \/>\n<meta property=\"og:url\" content=\"https:\/\/dialogue.earth\/en\/energy\/questions-over-rooppur-nuclear-power-plant-bangladesh\/\" \/>\n<meta property=\"og:site_name\" content=\"Dialogue Earth\" \/>\n<meta property=\"article:published_time\" content=\"2022-04-08T07:00:00+00:00\" \/>\n<meta property=\"article:modified_time\" content=\"2022-04-21T04:40:01+00:00\" \/>\n<meta property=\"og:image\" content=\"https:\/\/dialogue.earth\/content\/uploads\/2022\/04\/1200_20220407_Rooppur-nuclear-power-plant_Valery-Matytsin_Alamy_2CC9A35.jpg\" \/>\n\t<meta property=\"og:image:width\" content=\"1200\" \/>\n\t<meta property=\"og:image:height\" content=\"794\" \/>\n\t<meta property=\"og:image:type\" content=\"image\/jpeg\" \/>\n<meta name=\"author\" content=\"Joe Coroneo\" \/>\n<meta name=\"twitter:card\" content=\"summary_large_image\" \/>\n<meta name=\"twitter:title\" content=\"Questions over Russia-funded nuclear power plant in Bangladesh\" \/>\n<script type=\"application\/ld+json\" class=\"yoast-schema-graph\">{\"@context\":\"https:\/\/schema.org\",\"@graph\":[{\"@type\":\"Article\",\"@id\":\"https:\/\/dialogue.earth\/en\/energy\/questions-over-rooppur-nuclear-power-plant-bangladesh\/#article\",\"isPartOf\":{\"@id\":\"https:\/\/dialogue.earth\/en\/energy\/questions-over-rooppur-nuclear-power-plant-bangladesh\/\"},\"author\":{\"name\":\"Joe Coroneo\",\"@id\":\"https:\/\/dialogue.earth\/en\/#\/schema\/person\/41b5fa6bbd3a5a4f009440478f4f316f\"},\"headline\":\"Questions over Russia-funded nuclear power plant in Bangladesh\",\"datePublished\":\"2022-04-08T07:00:00+00:00\",\"dateModified\":\"2022-04-21T04:40:01+00:00\",\"mainEntityOfPage\":{\"@id\":\"https:\/\/dialogue.earth\/en\/energy\/questions-over-rooppur-nuclear-power-plant-bangladesh\/\"},\"wordCount\":1323,\"commentCount\":0,\"publisher\":{\"@id\":\"https:\/\/dialogue.earth\/en\/#organization\"},\"image\":{\"@id\":\"https:\/\/dialogue.earth\/en\/energy\/questions-over-rooppur-nuclear-power-plant-bangladesh\/#primaryimage\"},\"thumbnailUrl\":\"https:\/\/dialogue.earth\/content\/uploads\/2022\/04\/1200_20220407_Rooppur-nuclear-power-plant_Valery-Matytsin_Alamy_2CC9A35.jpg\",\"keywords\":[\"Energy transition\",\"Finance\",\"Fossil fuels\",\"Nuclear\"],\"articleSection\":[\"Energy\"],\"inLanguage\":\"en\",\"potentialAction\":[{\"@type\":\"CommentAction\",\"name\":\"Comment\",\"target\":[\"https:\/\/dialogue.earth\/en\/energy\/questions-over-rooppur-nuclear-power-plant-bangladesh\/#respond\"]}]},{\"@type\":\"WebPage\",\"@id\":\"https:\/\/dialogue.earth\/en\/energy\/questions-over-rooppur-nuclear-power-plant-bangladesh\/\",\"url\":\"https:\/\/dialogue.earth\/en\/energy\/questions-over-rooppur-nuclear-power-plant-bangladesh\/\",\"name\":\"Questions over Rooppur nuclear plant in Bangladesh | Dialogue Earth\",\"isPartOf\":{\"@id\":\"https:\/\/dialogue.earth\/en\/#website\"},\"primaryImageOfPage\":{\"@id\":\"https:\/\/dialogue.earth\/en\/energy\/questions-over-rooppur-nuclear-power-plant-bangladesh\/#primaryimage\"},\"image\":{\"@id\":\"https:\/\/dialogue.earth\/en\/energy\/questions-over-rooppur-nuclear-power-plant-bangladesh\/#primaryimage\"},\"thumbnailUrl\":\"https:\/\/dialogue.earth\/content\/uploads\/2022\/04\/1200_20220407_Rooppur-nuclear-power-plant_Valery-Matytsin_Alamy_2CC9A35.jpg\",\"datePublished\":\"2022-04-08T07:00:00+00:00\",\"dateModified\":\"2022-04-21T04:40:01+00:00\",\"description\":\"Officials are preparing to make up for an electricity shortfall if sanctions delay completion of Bangladesh's first nuclear power plant\",\"breadcrumb\":{\"@id\":\"https:\/\/dialogue.earth\/en\/energy\/questions-over-rooppur-nuclear-power-plant-bangladesh\/#breadcrumb\"},\"inLanguage\":\"en\",\"potentialAction\":[{\"@type\":\"ReadAction\",\"target\":[\"https:\/\/dialogue.earth\/en\/energy\/questions-over-rooppur-nuclear-power-plant-bangladesh\/\"]}]},{\"@type\":\"ImageObject\",\"inLanguage\":\"en\",\"@id\":\"https:\/\/dialogue.earth\/en\/energy\/questions-over-rooppur-nuclear-power-plant-bangladesh\/#primaryimage\",\"url\":\"https:\/\/dialogue.earth\/content\/uploads\/2022\/04\/1200_20220407_Rooppur-nuclear-power-plant_Valery-Matytsin_Alamy_2CC9A35.jpg\",\"contentUrl\":\"https:\/\/dialogue.earth\/content\/uploads\/2022\/04\/1200_20220407_Rooppur-nuclear-power-plant_Valery-Matytsin_Alamy_2CC9A35.jpg\",\"width\":1200,\"height\":794,\"caption\":\"2CC9A35 VOLGODONSK, ROSTOV-ON-DON REGION, RUSSIA - AUGUST 13, 2020: Shipment of a reactor pressure vessel and a steam generator from Atommash plant, a production branch of AEM-Technologies, for the first power unit of the Rooppur Nuclear Power Plant, which is currently under construction in Bangladesh. The first WWER-1200 reactor vessel manufactured by Atommash plant for non-CIS countries is over 330 tonnes in weight, 13 metres high and 4.5 metres in diameter. Valery Matytsin\/TASS\"},{\"@type\":\"BreadcrumbList\",\"@id\":\"https:\/\/dialogue.earth\/en\/energy\/questions-over-rooppur-nuclear-power-plant-bangladesh\/#breadcrumb\",\"itemListElement\":[{\"@type\":\"ListItem\",\"position\":1,\"name\":\"Home\",\"item\":\"https:\/\/dialogue.earth\/en\/\"},{\"@type\":\"ListItem\",\"position\":2,\"name\":\"Questions over Russia-funded nuclear power plant in Bangladesh\"}]},{\"@type\":\"WebSite\",\"@id\":\"https:\/\/dialogue.earth\/en\/#website\",\"url\":\"https:\/\/dialogue.earth\/en\/\",\"name\":\"Dialogue Earth\",\"description\":\"Global climate and environment news\",\"publisher\":{\"@id\":\"https:\/\/dialogue.earth\/en\/#organization\"},\"potentialAction\":[{\"@type\":\"SearchAction\",\"target\":{\"@type\":\"EntryPoint\",\"urlTemplate\":\"https:\/\/dialogue.earth\/en\/?s={search_term_string}\"},\"query-input\":{\"@type\":\"PropertyValueSpecification\",\"valueRequired\":true,\"valueName\":\"search_term_string\"}}],\"inLanguage\":\"en\"},{\"@type\":\"Organization\",\"@id\":\"https:\/\/dialogue.earth\/en\/#organization\",\"name\":\"\u5bf9\u8bdd\u5730\u7403\",\"url\":\"https:\/\/dialogue.earth\/en\/\",\"logo\":{\"@type\":\"ImageObject\",\"inLanguage\":\"en\",\"@id\":\"https:\/\/dialogue.earth\/en\/#\/schema\/logo\/image\/\",\"url\":\"https:\/\/dialogue.earth\/content\/uploads\/2024\/04\/Dialogue-Earth-Symbol-Logo_Black-Text.png\",\"contentUrl\":\"https:\/\/dialogue.earth\/content\/uploads\/2024\/04\/Dialogue-Earth-Symbol-Logo_Black-Text.png\",\"width\":256,\"height\":256,\"caption\":\"\u5bf9\u8bdd\u5730\u7403\"},\"image\":{\"@id\":\"https:\/\/dialogue.earth\/en\/#\/schema\/logo\/image\/\"},\"sameAs\":[\"https:\/\/twitter.com\/DialogueEarth_\",\"\",\"https:\/\/www.facebook.com\/DialogueEarth.English\",\"https:\/\/www.instagram.com\/dialogue.earth\/\",\"https:\/\/www.linkedin.com\/company\/dialogueearth\/\"],\"publishingPrinciples\":\"https:\/\/dialogue.earth\/en\/about\/\"},{\"@type\":\"Person\",\"@id\":\"https:\/\/dialogue.earth\/en\/#\/schema\/person\/41b5fa6bbd3a5a4f009440478f4f316f\",\"name\":\"Joe Coroneo\",\"description\":\"Joe Coroneo-Seaman is the Production Assistant at The Third Pole. He has lived and worked in Greater China for 2 years, and has an MA (Hons) in Chinese and French from the University of Edinburgh.\",\"url\":\"https:\/\/dialogue.earth\/en\/author\/joecoroneo\/\",\"sameAs\":[\"https:\/\/dialogue.earth\/en\/author\/kamran-reza-chowdhury\/\"]}]}<\/script>\n<!-- \/ Yoast SEO Premium plugin. -->","yoast_head_json":{"title":"Questions over Rooppur nuclear plant in Bangladesh | Dialogue Earth","description":"Officials are preparing to make up for an electricity shortfall if sanctions delay completion of Bangladesh's first nuclear power plant","robots":{"index":"index","follow":"follow","max-snippet":"max-snippet:-1","max-image-preview":"max-image-preview:large","max-video-preview":"max-video-preview:-1"},"canonical":"https:\/\/dialogue.earth\/en\/energy\/questions-over-rooppur-nuclear-power-plant-bangladesh\/","og_locale":"en_US","og_type":"article","og_title":"Questions over Russia-funded nuclear power plant in Bangladesh","og_description":"Officials are preparing to make up for an electricity shortfall if sanctions delay completion of the Rooppur nuclear power plant","og_url":"https:\/\/dialogue.earth\/en\/energy\/questions-over-rooppur-nuclear-power-plant-bangladesh\/","og_site_name":"Dialogue Earth","article_published_time":"2022-04-08T07:00:00+00:00","article_modified_time":"2022-04-21T04:40:01+00:00","og_image":[{"width":1200,"height":794,"url":"https:\/\/dialogue.earth\/content\/uploads\/2022\/04\/1200_20220407_Rooppur-nuclear-power-plant_Valery-Matytsin_Alamy_2CC9A35.jpg","type":"image\/jpeg"}],"author":"Joe Coroneo","twitter_card":"summary_large_image","twitter_title":"Questions over Russia-funded nuclear power plant in Bangladesh","schema":{"@context":"https:\/\/schema.org","@graph":[{"@type":"Article","@id":"https:\/\/dialogue.earth\/en\/energy\/questions-over-rooppur-nuclear-power-plant-bangladesh\/#article","isPartOf":{"@id":"https:\/\/dialogue.earth\/en\/energy\/questions-over-rooppur-nuclear-power-plant-bangladesh\/"},"author":{"name":"Joe Coroneo","@id":"https:\/\/dialogue.earth\/en\/#\/schema\/person\/41b5fa6bbd3a5a4f009440478f4f316f"},"headline":"Questions over Russia-funded nuclear power plant in Bangladesh","datePublished":"2022-04-08T07:00:00+00:00","dateModified":"2022-04-21T04:40:01+00:00","mainEntityOfPage":{"@id":"https:\/\/dialogue.earth\/en\/energy\/questions-over-rooppur-nuclear-power-plant-bangladesh\/"},"wordCount":1323,"commentCount":0,"publisher":{"@id":"https:\/\/dialogue.earth\/en\/#organization"},"image":{"@id":"https:\/\/dialogue.earth\/en\/energy\/questions-over-rooppur-nuclear-power-plant-bangladesh\/#primaryimage"},"thumbnailUrl":"https:\/\/dialogue.earth\/content\/uploads\/2022\/04\/1200_20220407_Rooppur-nuclear-power-plant_Valery-Matytsin_Alamy_2CC9A35.jpg","keywords":["Energy transition","Finance","Fossil fuels","Nuclear"],"articleSection":["Energy"],"inLanguage":"en","potentialAction":[{"@type":"CommentAction","name":"Comment","target":["https:\/\/dialogue.earth\/en\/energy\/questions-over-rooppur-nuclear-power-plant-bangladesh\/#respond"]}]},{"@type":"WebPage","@id":"https:\/\/dialogue.earth\/en\/energy\/questions-over-rooppur-nuclear-power-plant-bangladesh\/","url":"https:\/\/dialogue.earth\/en\/energy\/questions-over-rooppur-nuclear-power-plant-bangladesh\/","name":"Questions over Rooppur nuclear plant in Bangladesh | Dialogue Earth","isPartOf":{"@id":"https:\/\/dialogue.earth\/en\/#website"},"primaryImageOfPage":{"@id":"https:\/\/dialogue.earth\/en\/energy\/questions-over-rooppur-nuclear-power-plant-bangladesh\/#primaryimage"},"image":{"@id":"https:\/\/dialogue.earth\/en\/energy\/questions-over-rooppur-nuclear-power-plant-bangladesh\/#primaryimage"},"thumbnailUrl":"https:\/\/dialogue.earth\/content\/uploads\/2022\/04\/1200_20220407_Rooppur-nuclear-power-plant_Valery-Matytsin_Alamy_2CC9A35.jpg","datePublished":"2022-04-08T07:00:00+00:00","dateModified":"2022-04-21T04:40:01+00:00","description":"Officials are preparing to make up for an electricity shortfall if sanctions delay completion of Bangladesh's first nuclear power plant","breadcrumb":{"@id":"https:\/\/dialogue.earth\/en\/energy\/questions-over-rooppur-nuclear-power-plant-bangladesh\/#breadcrumb"},"inLanguage":"en","potentialAction":[{"@type":"ReadAction","target":["https:\/\/dialogue.earth\/en\/energy\/questions-over-rooppur-nuclear-power-plant-bangladesh\/"]}]},{"@type":"ImageObject","inLanguage":"en","@id":"https:\/\/dialogue.earth\/en\/energy\/questions-over-rooppur-nuclear-power-plant-bangladesh\/#primaryimage","url":"https:\/\/dialogue.earth\/content\/uploads\/2022\/04\/1200_20220407_Rooppur-nuclear-power-plant_Valery-Matytsin_Alamy_2CC9A35.jpg","contentUrl":"https:\/\/dialogue.earth\/content\/uploads\/2022\/04\/1200_20220407_Rooppur-nuclear-power-plant_Valery-Matytsin_Alamy_2CC9A35.jpg","width":1200,"height":794,"caption":"2CC9A35 VOLGODONSK, ROSTOV-ON-DON REGION, RUSSIA - AUGUST 13, 2020: Shipment of a reactor pressure vessel and a steam generator from Atommash plant, a production branch of AEM-Technologies, for the first power unit of the Rooppur Nuclear Power Plant, which is currently under construction in Bangladesh. The first WWER-1200 reactor vessel manufactured by Atommash plant for non-CIS countries is over 330 tonnes in weight, 13 metres high and 4.5 metres in diameter. Valery Matytsin\/TASS"},{"@type":"BreadcrumbList","@id":"https:\/\/dialogue.earth\/en\/energy\/questions-over-rooppur-nuclear-power-plant-bangladesh\/#breadcrumb","itemListElement":[{"@type":"ListItem","position":1,"name":"Home","item":"https:\/\/dialogue.earth\/en\/"},{"@type":"ListItem","position":2,"name":"Questions over Russia-funded nuclear power plant in Bangladesh"}]},{"@type":"WebSite","@id":"https:\/\/dialogue.earth\/en\/#website","url":"https:\/\/dialogue.earth\/en\/","name":"Dialogue Earth","description":"Global climate and environment news","publisher":{"@id":"https:\/\/dialogue.earth\/en\/#organization"},"potentialAction":[{"@type":"SearchAction","target":{"@type":"EntryPoint","urlTemplate":"https:\/\/dialogue.earth\/en\/?s={search_term_string}"},"query-input":{"@type":"PropertyValueSpecification","valueRequired":true,"valueName":"search_term_string"}}],"inLanguage":"en"},{"@type":"Organization","@id":"https:\/\/dialogue.earth\/en\/#organization","name":"\u5bf9\u8bdd\u5730\u7403","url":"https:\/\/dialogue.earth\/en\/","logo":{"@type":"ImageObject","inLanguage":"en","@id":"https:\/\/dialogue.earth\/en\/#\/schema\/logo\/image\/","url":"https:\/\/dialogue.earth\/content\/uploads\/2024\/04\/Dialogue-Earth-Symbol-Logo_Black-Text.png","contentUrl":"https:\/\/dialogue.earth\/content\/uploads\/2024\/04\/Dialogue-Earth-Symbol-Logo_Black-Text.png","width":256,"height":256,"caption":"\u5bf9\u8bdd\u5730\u7403"},"image":{"@id":"https:\/\/dialogue.earth\/en\/#\/schema\/logo\/image\/"},"sameAs":["https:\/\/twitter.com\/DialogueEarth_","","https:\/\/www.facebook.com\/DialogueEarth.English","https:\/\/www.instagram.com\/dialogue.earth\/","https:\/\/www.linkedin.com\/company\/dialogueearth\/"],"publishingPrinciples":"https:\/\/dialogue.earth\/en\/about\/"},{"@type":"Person","@id":"https:\/\/dialogue.earth\/en\/#\/schema\/person\/41b5fa6bbd3a5a4f009440478f4f316f","name":"Joe Coroneo","description":"Joe Coroneo-Seaman is the Production Assistant at The Third Pole. He has lived and worked in Greater China for 2 years, and has an MA (Hons) in Chinese and French from the University of Edinburgh.","url":"https:\/\/dialogue.earth\/en\/author\/joecoroneo\/","sameAs":["https:\/\/dialogue.earth\/en\/author\/kamran-reza-chowdhury\/"]}]}},"_links":{"self":[{"href":"https:\/\/dialogue.earth\/en\/wp-json\/wp\/v2\/posts\/20086190","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/dialogue.earth\/en\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/dialogue.earth\/en\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/dialogue.earth\/en\/wp-json\/wp\/v2\/users\/20000283"}],"replies":[{"embeddable":true,"href":"https:\/\/dialogue.earth\/en\/wp-json\/wp\/v2\/comments?post=20086190"}],"version-history":[{"count":0,"href":"https:\/\/dialogue.earth\/en\/wp-json\/wp\/v2\/posts\/20086190\/revisions"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/dialogue.earth\/en\/wp-json\/wp\/v2\/media\/20086240"}],"wp:attachment":[{"href":"https:\/\/dialogue.earth\/en\/wp-json\/wp\/v2\/media?parent=20086190"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/dialogue.earth\/en\/wp-json\/wp\/v2\/categories?post=20086190"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/dialogue.earth\/en\/wp-json\/wp\/v2\/tags?post=20086190"},{"taxonomy":"hashtags","embeddable":true,"href":"https:\/\/dialogue.earth\/en\/wp-json\/wp\/v2\/hashtags?post=20086190"},{"taxonomy":"country","embeddable":true,"href":"https:\/\/dialogue.earth\/en\/wp-json\/wp\/v2\/country?post=20086190"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}