Energy

Private dam builders back out of Brahmaputra dams

Arunachal Pradesh’s ‘dam rush’ seems to be over with most private players yet to start on the projects and asking the public sector to take over
<p>The Brahmaputra flows from eastern Tibet and Arunachal Pradesh where 160 large dams are planned (Rita Willaert )</p>

The Brahmaputra flows from eastern Tibet and Arunachal Pradesh where 160 large dams are planned (Rita Willaert )

Residents of northeast India’s Arunachal Pradesh had long been concerned over the scores of hydropower projects proposed for their state. But the frenetic rush, it seems, is over with private companies that had earlier queued up to build dams in the state losing interest and asking the public sector National Hydel Power Corporation (NHPC) to take over their projects.

By 2009 Arunachal Pradesh had signed 153 memorandums of understanding (MoU) to generate over 43,000 MW of electricity, pushing aside environmental concerns and the risks posed by clustering dams. Six dams, for instance, were proposed on the Lohit river – a tributary of the Brahmaputra which rises in eastern Tibet. Work on most projects, however, is yet to take off.

Last year, Chief Minister Nabam Tuki said that the state had signed pacts with power developers to execute 160 projects with a total capacity of 46,948 MW. He said directions had been given to power developers to start work but also admitted that several MoUs and memorandums of association (MoAs) had “been cancelled”.

arunachal pradesh map hydropower

 

A senior official of the NHPC said on condition of anonymity, “Private companies have approached us to take over their projects or work in association (with them) on their hydel power projects. Their main concern is that they now don’t see these projects as cost-effective, and therefore want to pull out.”

He steered clear of confirming whether NHPC had agreed to take over private sector projects and stressed that the public sector undertaking (PSU) was focussed on its own projects at the moment.

“We are focussing on two projects at the moment. There is a 1,400 MW project in Tawang, and a 2,000 MW project in Subansiri. The Subansiri project had some hurdles, but we are working on allaying the fears and misconceptions of people regarding its downstream impact; 50% work on this project is already done,” he said.

The lower Subansiri hydropower project in Arunachal Pradesh has been held up by protests from people in downriver Assam who have expressed concerns over their livelihood and fears of catastrophic floods in the event of an earthquake, which is a major risk in the area.

The NHPC official, however, assured that “fears are being addressed and work is in progress”.

“Work will start full-swing once the (Assam assembly) elections are over,” he said, adding that they could also start work on another hydropower project on the Dibang river. The polls are scheduled this year.

Private players face hurdles

One of the private players, Jindal Power Limited (JPL), which has three projects in Arunachal Pradesh — 3,097 MW in Etalin, 1,800 MW in Kamala, and 680 MW in Attunli —is now looking at “associating” with public sector bodies like NHPC. Asked why, a JPL spokesperson said, “These projects are currently under various stages of development and JPL is exploring prudent avenues of association to unlock shareholder value and build hydro-electric energy assets for the nation.”

Other private players talk about lack of roads and power lines in some places, frequent outbreak of protests from locals and environmentalists, and regulatory hurdles that have delayed these projects. As constant delays have led to cost overruns, private players have started seeing these projects as less attractive.

One NHPC official said, “Most of these projects are storage dams which are of a certain height while the reservoir is at a lower level. This causes loss of (electricity) generating capacity. Public sector units can afford to maintain this lower level in order to mitigate the threat of floods, but private sector companies cannot afford this loss.”

In January there was a large protest in Tawang led by Buddhist monks, saying no to large dams in an “ecologically, culturally, and strategically sensitive district”. The protestors claimed that improper maintenance of the 25 current small and mini hydropower projects had led to a power crisis in the district. If these are maintained well, they said, there would be no need of bigger dams to meet the power requirement.

‘Mess in process’

Himanshu Thakkar, coordinator of South Asia Network on Dams, Rivers and People (SANDRP), termed the various hydropower projects in the state as a “mess in process”. “Despite all the MoUs signed, barring two-three, none of the other projects have started in Arunachal Pradesh. This is because the decision making process in itself was flawed — the community impact assessment was false, it did not involve the local community,” he said.

“When the private companies rushed in to sign those projects, in the period between 2005 and 2010, the demand for electricity was high. There was no risk for the private companies. The financial risk was borne by the government and the environmental risk by the locals. So courier companies, tobacco companies, hotel industry, everyone rushed in to sign contracts. But now the price of electricity has dropped. In the east, it’s less than a rupee per unit. The future does not look bright for them, especially because solar power is coming up,” Thakkar said. He added that NHPC was “struggling with its own projects”, referring in particular to the lower Subansiri project.

Between demands of “no more dams” and private players hoping to either withdraw or get into a joint venture, the fate of these projects looks uncertain for a long time to come.

-->
Cookies Settings

Dialogue Earth uses cookies to provide you with the best user experience possible. Cookie information is stored in your browser. It allows us to recognise you when you return to Dialogue Earth and helps us to understand which sections of the website you find useful.

Required Cookies

Required Cookies should be enabled at all times so that we can save your preferences for cookie settings.

Dialogue Earth - Dialogue Earth is an independent organisation dedicated to promoting a common understanding of the world's urgent environmental challenges. Read our privacy policy.

Cloudflare - Cloudflare is a service used for the purposes of increasing the security and performance of web sites and services. Read Cloudflare's privacy policy and terms of service.

Functional Cookies

Dialogue Earth uses several functional cookies to collect anonymous information such as the number of site visitors and the most popular pages. Keeping these cookies enabled helps us to improve our website.

Google Analytics - The Google Analytics cookies are used to gather anonymous information about how you use our websites. We use this information to improve our sites and report on the reach of our content. Read Google's privacy policy and terms of service.

Advertising Cookies

This website uses the following additional cookies:

Google Inc. - Google operates Google Ads, Display & Video 360, and Google Ad Manager. These services allow advertisers to plan, execute and analyze marketing programs with greater ease and efficiency, while enabling publishers to maximize their returns from online advertising. Note that you may see cookies placed by Google for advertising, including the opt out cookie, under the Google.com or DoubleClick.net domains.

Twitter - Twitter is a real-time information network that connects you to the latest stories, ideas, opinions and news about what you find interesting. Simply find the accounts you find compelling and follow the conversations.

Facebook Inc. - Facebook is an online social networking service. China Dialogue aims to help guide our readers to content that they are interested in, so they can continue to read more of what they enjoy. If you are a social media user, then we are able to do this through a pixel provided by Facebook, which allows Facebook to place cookies on your web browser. For example, when a Facebook user returns to Facebook from our site, Facebook can identify them as part of a group of China Dialogue readers, and deliver them marketing messages from us, i.e. more of our content on biodiversity. Data that can be obtained through this is limited to the URL of the pages that have been visited and the limited information a browser might pass on, such as its IP address. In addition to the cookie controls that we mentioned above, if you are a Facebook user you can opt out by following this link.

Linkedin - LinkedIn is a business- and employment-oriented social networking service that operates via websites and mobile apps.