Business

Weak case for UK’s China-funded nuclear plant, say critics

The UK is pushing ahead with new Hinkley plant despite bloated costs and unproven technology 
English

The UK and China moved closer this week to finalising the finance of a highly controversial plan to build the first new nuclear power plant in the UK for a generation. The plant, Hinkley Point C in Somerset, western England, is seeking Chinese finance for a French design that has never been successfully built.

On a trip to Beijing, Chancellor of the Exchequer George Osborne said Chinese participation could enable the country to develop and own at least one other UK nuclear plant at Bradwell, a site earmarked for development in eastern England.

As currently outlined, Hinkley will produce the world’s most expensive electricity. It is also facing mounting opposition in the UK for both technical and financial reasons. Lord Turnbull, a former Permanent Secretary to the Treasury, one of the country’s  top civil servants, has predicted that it will be “a kind of bottomless pit and a big white elephant.”

The chief executive of the energy supplier RWE Npower, Paul Massara, has also condemned the Hinkley Point plans as an “expensive mistake” that could haunt “our children’s children”. Independent energy price comparison site energyhelpline.com has claimed that it would cost UK consumers an additional £5.2 billion (51.4 billion yuan) per year on top of current electricity costs.
The technical objections begin with the fact that the design, which was drawn up by troubled French company Areva, has never been successfully built, and the contractor Electricite de France (EDF) seems increasingly uncertain that it is possible. In the first attempt, in Finland, construction of the Olkiluoto reactor began in 2005 and was expected to be completed in 2009 at cost of €3 billion. The latest revision to the schedule puts the completion back to 2018 and the latest estimated total cost of the project has ballooned to €8.5 billion.
A second project, at Flamanville in France, was scheduled to start in July 2005 and enter production in 2012 at a cost of €3 billion. This month, that was revised to a 2018 start with costs of €10.5 billion.  The Taishan 1 and 2 reactors that are of a similar design to those earmarked for Hinkley have also been hindered by delays and cost overruns. Construction of the plant, which began in 2009/10 had a scheduled completion date of 2014 but that has been put back until 2016, while there is little idea of what the extra costs for the delayed project will be. There are no reliable data on costs in China.
Doubts are also growing in the UK that the country needs new nuclear power to meet its energy requirements. Overall demand is falling as efficiency improves, and greater connectivity with continental Europe gives the UK access to cheaper electricity. The UK government has guaranteed a so-called strike price for energy produced at Hinkley Point C —  if it is ever completed  —  of nearly three times the current UK wholesale price. While it is not easy to predict future wholesale energy prices, there are good reasons to suppose that they will continue to fall in Europe as investment in renewables begins to yield dividends.
Supporters of new nuclear in Britain argue that, despite the spectacular growth of renewables in Europe, the UK still needs baseload power to guarantee supplies when renewables do not perform. But, increasingly, this view appears technically out of date, and risks holding the country back from reaping the full benefits of the renewables revolution.
Antony Froggatt, an expert on energy policy at the Royal Institute for International Affairs (Chatham House) told chinadialogue: “The question is, what capacity do you need? The UK has a binding renewables target, so we have to increase renewable energy. We are taking coal off (the grid) and we have life extensions on current nuclear plants. The question is, can the system cope with shortages in cold winters? But with the new interconnections, there are more opportunities for balancing (supply with demand). There are many studies that say that the idea of baseload is dead.”
Trade-off
Even if baseload was still required, Froggatt argues, the expense of Hinkley Point C is hard to justify. Investment bankers and financial analysts, Liberum Capital, points out that for £16 billion, for which Hinkley Point promises 3,200MW,  the UK could build 27,000MW of new CCGT gas fired power stations – more than nine times the output.
Not only would this be much cheaper, but it would avoid the unknowable future costs of decommissioning and nuclear waste storage, and, because of the greater flexibility of gas, would not block the addition of new renewables to the grid.  Nuclear plants, on the other hand, are inflexible in output and make balancing the grid more difficult. Energy experts argue that new nuclear is an old-fashioned energy option that could lock in obsolescence at a time of rapid transition in both energy generation and distribution.
Liberum Capital has described Hinkley Point C as “a massive bet” that fossil fuel prices will be extremely high in the future.  If that bet proves to be wrong, their analysis continues, “then this contract will look economically insane when HPC commissions”. It added: “We are frankly staggered that the UK government thinks it is appropriate to take such a bet and underwrite the economics of any power station that costs £5 million  per MW and takes 9 years to build.”
Concerns

HSBC, the bank that served as adviser to the project, is also highly critical, listing eight concerns about Hinkley Point C in a report in July 2015. These concerns included forecast falls in UK power demand, increasing availability of  interconnections to Europe that will transform the country’s ’s electricity landscape, overcapacity in Europe which will bring prices down further, the poor track record of the design and the possibility of legal challenge to the deal.  “The outlook for sluggish power prices will make the strike price of upcoming Hinkley power look increasingly prohibitive,” the HSBC report added.

Even before construction starts, the predicted generating cost of Hinkley Point C has risen sharply. In 2004, EDF estimated the generating cost of a limited series of four reactors , at £27 per MWh  (at 2004 values;  or £37.2 at 2013 values). By 2012, this had nearly quadrupled to £92.5 per MWh (at 2012 values) for two units and £89.5 per MWh for four reactors. The expected cost  at the start of operations, at the time scheduled for 2024, was £121 per MWh. Since then, EDF has announced further delays to the project, which will certainly have cost implications.

Costs spiral

The cost of construction has shown an equally rapid upward trend.  In 2008, the UK government’s cost benefit analysis assumed construction costs of £1,250/kW, plus costs for interest during construction and onsite waste storage, giving a total cost of £2.8 billion to build the 1.6 GW reactor.   By 2013, this had risen from £12 billion to £14 billion, according to the government and £16 billion for two units, according to EDF.
A year later, the European Commission said that the plant would require debt financing of around £17 billion (around €21.6 billion) and would eventually have a capital spend of about £34 billion (around €43 billion). The construction costs are estimated at £24.5 billion (around €31.2 billion). The cost is far higher than the £16 billion previously cited by developer EDF Energy, according to the EC, predominantly because it includes, for the first time, the interest costs during the decade-long construction period.
A tenfold increase in costs, and falling wholesales energy prices ought to trigger a revised cost-benefit calculation. Liberum Capital estimates the investment return for the troubled French company EDF at between 10% and 14%, with the UK taxpayer bearing the major part of the risk.
Nor have the legal challenges gone away. The Austrian chancellor, Werner Faymann, has complained that Hinkley sets a “bad precedent” because guaranteeing payment for a mature and unsustainable technology breaks EU rules. Austria has announced that it will bring a legal challenge to the massive subsidy the UK government proposes.
Risks mount
Meanwhile, in the wake of delays at Flamanville, EDF has promised a new design, but it will not be ready in time to be used at Hinkley Point. Nick Butler, a former  energy adviser to prime ministers, has written: “The deal will go down in history…as an example of the inability of the British government – ministers and civil servants alike – to negotiate complex commercial deals.”
There are risks, too, for the Chinese government, which is keen to secure future contracts to build its own reactors in the UK. Involvement with a project that is so widely criticised, even by those who support nuclear power in principle, could raise doubts about China as a responsible partner for a new nuclear age and cast a shadow over the forthcoming visit to the UK by Chinese president Xi Jinping. The controversy over Hinkley Point C is likely to grow as the costs escalate and the technical difficulties remain unresolved. Few of those involved in the project are likely to emerge with their reputations intact.